S-34.1, r. 3 - Regulation respecting petroleum exploration, production and storage licences, and the pipeline construction or use authorization

Full text
185. Every person who, on 20 September 2018, is responsible for a pipeline that is not used must so notify the Minister within 180 days following that date.
The notice must contain the name and contact information of the person responsible and be accompanied by a map at a scale of 1:10,000 showing the installations and the route of the pipeline and all its elements.
O.C. 1253-2018, s. 185.
In force: 2018-09-20